Invitation for Bids for Weakley Street Improvement Federal-Aid Project No. CML-5168(032)
1. General Information
PUBLIC NOTICE IS HEREBY GIVEN THAT the City of Calexico is inviting bids for the Weakley Street Improvement Project in the City of Calexico. The Project consist of cutting/removal of existing subgrade soil, scarification/re-grading of remaining subgrade soil, procurement and placement of imported base, procurement and placement of asphalt concrete and ARHM overlay, procurement and construction of concrete curb, gutter, sidewalk, driveways, and curb ramps, replacement of existing utilities and construction of new utilities (including water services, sewer services, and street lights), adjustment of existing utility lids to grade, coordination with IID for the relocation of existing power/telephone poles, and stop legend striping.
2. Scope of Work
The work shall be done in conformance with the Plans and Specifications for the Project. The Project includes the following major tasks:
- Demolition/clearing of existing debris, concrete slab, tree stump, removal of existing subgrade, scarification of remaining subgrade, and re-compaction to receive new base material.
- Procurement and construction of new base & asphalt pavement.
- Procurement and construction of new concrete improvements, including curb & gutter, sidewalk, driveways, and curb ramps.
- Procurement and construction of new utilities (water service laterals, sewer laterals, & street lights).
- Relocation of existing power poles and overhead conduits/wire
3. Engineer’s Cost Estimate
Bidders shall take notice hereto that the Engineer’s Cost Estimate for the construction of the Base-Bid Work is approximately $812,000. For the Alternate Bid Work, the estimated construction cost is $246,000.
4. Construction Schedule
The overall construction contract duration is sixty (60) working days from the Notice to Proceed. Due to potential supply chain issues, Contractor shall provide submittals for review and approval by the Engineer within one (1) week of contract execution by the City. If it is determined that any items impact schedule completion, Contractor to notify City immediately.
5. Pre-bid Meeting
A non-mandatory pre-bid meeting shall be held on Friday, April 24, 2026 at 10:00 am. While the meeting is not mandatory, bidders are encouraged to participate in the meeting because it affords an opportunity to become more familiar with the scope of work for the Project, the Project’s key areas, and other administrative and procedural requirements. Potential bidders are encouraged to attend. The meeting will take place at the offices of the Public Works Department:
City Public Works Office
549 Pierce Ave
Calexico, 92231
6. Addenda
The correction of any discrepancies or omissions from the specifications or other contract documents or any interpretation thereof during the bidding period shall be made only by written addendum. A completed and signed Addenda Acknowledgement Form shall be included in the Bid Proposal.
7. Bidding Instructions, Project’s Available Supporting Documents
(a) SEALED PROPOSAL will be accepted at the Office of the City Clerk, City Hall, 608 Heber Avenue, Calexico, California until 3:00 p.m., on Thursday, May 7, 2026, at which time all proposals will be publicly opened and read aloud. LATE BIDS WILL NOT be accepted and will be considered unresponsive.
(b) Each bid shall be submitted in a sealed envelope bearing on the outside the name of the bidder, his/her address, and the name of the project for which the bid is submitted. If forwarded by mail, the sealed envelope containing the bid shall be enclosed in another envelope addressed as specified in the bid form.
(c) No bid shall be received unless it is made using the format specified in this Invitation to Bid and Technical Specifications. Each bid must be accompanied by a guaranty of cash, certified check, and cashier check or bidders' bond made payable to the City of Calexico for an amount equal to at least ten percent (10%) of the bid. Such guaranty to be forfeited should the bidder to whom the contract is awarded fails to enter the contract. All guaranties are to be returned after the contract is awarded.
(d) The bid may be considered incomplete and be disqualified if any of the items (or related attachments/forms) within the Bid Proposal are not provided.
(e) The City of Calexico has a Disadvantaged Business Enterprise (DBE) goal of ten (10) percent (10%). Per Caltrans’ Bulletin 25-07 R3, this requirement is currently on-hold.
(f) This is a City Public Works Department project, which is exclusively being funded with State/Federal public funds. Accordingly, it is subject to prevailing wages laws and regulations. Pursuant to Labor Code §1773, the general prevailing wage rates in the county, in which the work is to be done have been determined by the Director of the California Department of Industrial Relations. These wages are set forth in the General Prevailing Wage Rates for this project, available at City of Calexico address and available from the California Department of Industrial Relations' Internet web site at http://www.dir.ca.gov/DLSR/PWD. The applicable Federal minimum wage rates as predetermined by the United States Secretary of Labor are available at the City of Calexico Public Works Department. In addition, a copy may be examined at the offices described above where project plans, special provisions, and bid forms may be seen. Revisions to the applicable Federal Wage Rates, up to ten (10) days before bid opening, shall be identified by the issuance of an addendum with the corresponding Internet Website address of where the revisions can be found. The final contract documents signed by the City and the contractor shall include the Federal Wage Rates, or the Federal Wage Rates as revised by addendums, if any such addendums have been issued. Future effective general prevailing wage rates, which have been predetermined and are on file with the California Department of Industrial Relations are referenced but not printed in the general prevailing wage rates.
Attention is directed to the Federal minimum wage rate requirements in the Contract Documents. If there is a difference between the minimum wage rates predetermined by the Secretary of Labor and the general prevailing wage rates determined by the Director of the California Department of Industrial Relations for similar classifications of labor, the Contractor and subcontractors shall pay not less than the higher wage rate. The Department will not accept lower State wage rates not specifically included in the Federal minimum wage determinations. This includes "helper" (or other classifications based on hours of experience) or any other classification not appearing in the Federal wage determinations. Where Federal wage determinations do not contain the State wage rate determination otherwise available for use by the Contractor and subcontractors, the Contractor and subcontractors shall pay not less than the Federal minimum wage rate, which most closely approximates the duties of the employees in question.
(g) The U.S. Department of Transportation ("DOT") provides a toll-free hotline service to report bid rigging activities. Bid rigging activities can be reported Monday through Friday, between 8:00 a.m. and 5:00 p.m., Eastern Standard Time at 800/424-9071. Anyone with knowledge of possible bid rigging, bidder collusion, or other fraudulent activities should use the hotline to report these activities. The hotline is part of DOT's continuing effort to identify and investigate highway construction contract fraud and abuse and is operated under the direction of the DOT Inspector General. All information will be treated confidentially and caller anonymity will be respected.
(h) A bid will only be accepted from a Contractor who is licensed in accordance with the provisions of Chapter 9, Division 3, of the Business and Professions Code of the State of California as amended. In addition, the Contractor, sub-contractors, and suppliers shall also have a business license issued by the City prior to commencing work.
(i) Electronic version on the approved plans and specifications, geotechnical reports for the Project, groundwater quality results in the area of the Project, and photos/displays of certain Project areas may be obtained by visiting the City’s website at: https://www.calexico.ca.gov/bidsandrfps.
(j) Special attention of all prospective bidders is called to the Construction Schedule and the Bid Requirements and General Conditions Articles of this document for full directions as to bidding, etc.
(k) Pre-Bid inquires must be submitted to Jesus Villegas Peimbert, Public Works Director/City Engineer via email at jvillegas@calexico.ca.gov by 5:00 p.m. on Tuesday, April 28, 2026.
8. Bid Evaluation and Award of Construction Contract
(a) All bids are to be compared based on the Engineer’s Cost Estimate for the Project and estimate of the quantities of work to be done.
(a) A summary of the bids along with a recommended bid may be presented to the City Council for its consideration of awarding the Project’s construction contract at a Public Meeting, after the bids are received and evaluated, in the City Council Chambers, 608 Heber Avenue, Calexico, California.
(b) No contractor or subcontractor may be awarded a contract for public work on a public works project (awarded on or after April 1, 2015) unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5. This Project is subject to compliance monitoring and enforcement by the Department of Industrial Relations.
(c) The RFB, Plans, Specifications, Addendums, and any other Bid Documents can be found at City’s website at https://www.calexico.ca.gov/bidsandrfps.
(d) If bidder is a corporate entity and is awarded the contract, prior to execution of the contract, Contractor shall submit satisfactory, documentary proof that the person(s) executing said contract on the behalf of said corporation has authority to do so.
CITY'S RIGHT RESERVED: The City reserves the right to reject any or all bids, to waive any informality in a bid, and to make awards in the interest of the City.
Benjamin Martinez
City Manager City of Calexico